Laying the junior classroom floors
February 2001

The concrete bases for the junior classroom floors were laid.
Firstly the area was flattened and a plastic floor was laid.

Next a wire mesh was put in to reinforce the concrete.
Just before the floors were laid, the steelwork for the building frame arrived.
You can see the crane in this picture.
NEXT: The steel framework